Arizona State University Stadium

Tempe, Arizona

Project Overview

The ASU Stadium project operated under an expedited schedule to ensure the facility was ready for the 2018-19 football season. Despite facing significant challenges, including high temperatures reaching 120 degrees, Intermark Steel demonstrated remarkable resilience. The project involved two shifts running 24 hours a day for three months, showcasing the team’s dedication to meeting tight deadlines. While Intermark incurred losses on this project, the experience provided invaluable insights into working in Arizona and utilizing union labor. These lessons positioned the company for greater success in future projects. The enormity of the task tested Intermark’s commitment and determination, solidifying their reputation for perseverance in challenging conditions.

Project Details

Completed

2019

Services

Stairs, Railings, Structural, Misc.

Contractor

Schuff Steel, Huff Construction

Location

Tempe, Arizona

Project Photos

Project Video